Setting up a simple asset register for a school, church or council building
What to put in an asset register, which equipment to start with, and the inspection duties — lifts, work equipment, electrical equipment, fire safety, water — that make it worth keeping.
- Where it applies
- Great Britain
- Checked against its sources
- 7 November 2026
An asset register is a list of the equipment you are responsible for, with enough about each item to look after it. It sounds like paperwork, and the first version often is. A good one is the thing you reach for when a boiler fails at 7am, when an inspector asks when the lift was last examined, or when you hand the job to someone else. This guide covers what to record, where to start, and the legal duties in Great Britain that a register helps you keep.
No law says “keep an asset register” — but several assume one
There is no single regulation requiring a small organisation to keep an asset register. What the law does require is that particular equipment is maintained, examined or tested, and you cannot show that without knowing what you have. Four duties come up in almost every school, church or council building:
Work equipment must be maintained
The Provision and Use of Work Equipment Regulations 1998, regulation 5 requires every employer to ensure “that work equipment is maintained in an efficient state, in efficient working order and in good repair”, and that where machinery has a maintenance log, “the log is kept up to date.” Work equipment covers far more than machines: mowers, ladders, kitchen equipment and power tools all count.
Lifts and lifting equipment must be thoroughly examined
The Lifting Operations and Lifting Equipment Regulations 1998, regulation 9 sets fixed intervals for lifting equipment exposed to conditions that cause deterioration. It must be thoroughly examined:
- at least every 6 months for equipment that lifts people, and for lifting accessories;
- at least every 12 months for other lifting equipment;
- or in line with an examination scheme drawn up by a competent person;
- and after any exceptional circumstances liable to affect its safety.
A passenger lift is equipment for lifting people, so where this part of the regulation applies its interval is 6 months. If you are unsure whether a piece of equipment falls under the Regulations, ask a competent person. A register that holds each item’s last examination date makes the next one hard to miss.
Electrical equipment must be kept safe — but annual PAT is not the law
The Electricity at Work Regulations 1989 require electrical equipment that could cause injury to be maintained in a safe condition. HSE’s own answers on portable appliance testing are blunt about what that does not mean: the Regulations “do not specify what needs to be done, by whom or how frequently”, PAT is not compulsory, and there is no legal requirement to label tested equipment or keep records of tests.
HSE’s advice is to take a risk-based approach: a kettle or floor cleaner that is moved and used heavily needs more attention than a desktop computer that never leaves its desk. A register lets you set a different interval for each, and HSE notes that records and labels are “a useful management tool” even where they are not required.
Fire safety equipment must be maintained
In England and Wales, Article 17 of the Regulatory Reform (Fire Safety) Order 2005 requires equipment provided for fire safety — alarms, emergency lighting, extinguishers, fire doors — to be subject to “a suitable system of maintenance”. Our guide to fire alarm and emergency lighting testing covers the intervals.
Hot and cold water systems carry their own monitoring duty for legionella, with records of checks kept for at least five years — see our guide to legionella water temperature checks.
What to record for each asset
Start small. Each column you add is one you have to keep up to date, so begin with the ones that answer real questions:
| Field | Why |
|---|---|
| Name | What people call it — “Boiler 1, main school”, not a model number |
| Location | Building and room, so someone new can find it |
| Make, model and serial | What a contractor asks for first, and what a recall notice names |
| Installed or bought | How old it is, for planning when to replace it |
| Who services it | The contractor and their number, or “in-house” |
| Statutory checks | What has to be examined or tested, how often, and under which rule |
| Last and next check | The dates that actually keep you compliant |
| Criticality | What happens if it fails: closure, inconvenience, or nothing much |
| Documents | Manuals, certificates and the last examination report |
Two fields earn their place quickly. Criticality decides what to fix first when three things break in a week. Parent — the boiler a pump belongs to, the building a boiler is in — lets you see everything that went wrong in one plant room, and stops the register becoming a flat list of a thousand lines.
What to put on it first
Not everything belongs in the register. A useful test: would you ever need to know the history of this item? A boiler, yes. A light bulb, no. A sensible order to work through:
- Anything with a required inspection or test: lifts and lifting equipment, the fire alarm panel, emergency lighting, extinguishers, the water system’s sentinel outlets.
- Anything whose failure closes a building: heating plant, water heaters, the main electrical distribution board, kitchen equipment if you serve meals.
- Anything expensive to replace: roofs and windows by elevation, minibuses, grounds equipment, sound systems in a church.
- Everything else, as you meet it — add an item the first time you raise a repair against it.
The fourth step is how most registers actually get finished. Nobody has a free week to survey a building, but everybody repairs things.
Keeping it alive
A register decays the moment it is finished unless it is part of the work rather than beside it:
- Raise every repair against an asset. The register then fills with history on its own, and the item that has failed six times this year shows itself.
- Put each statutory check on a schedule so the next date is calculated, not remembered.
- Label the asset. A small QR label on a boiler or a lift lets the engineer open the record on the spot, and lets anyone report a fault against the right item.
- Review it once a year: what was disposed of, what was added, and whether any interval should change based on what failed.
Sitekeep is built around this: each asset has a location, a parent, a criticality and its own work order history; preventive maintenance schedules generate the recurring checks; and it prints a QR label for each asset, so a colleague who scans it reaches the record and anyone else can report a problem with it.
Sources
- The Provision and Use of Work Equipment Regulations 1998, regulation 5, legislation.gov.uk.
- The Lifting Operations and Lifting Equipment Regulations 1998, regulation 9, legislation.gov.uk — the 6- and 12-month thorough examinations.
- PAT — portable appliance testing FAQs, HSE, updated 16 April 2025.
- The Regulatory Reform (Fire Safety) Order 2005, article 17, legislation.gov.uk (England and Wales).
- Legionnaires’ disease: a brief guide for dutyholders (INDG458), HSE — record retention.
This guide explains what the law and the regulator say; it is not legal advice. Where a figure matters to your building, read the source it links to and your own risk assessment.